There’s nothing quite like kicking
back on your own patio—until the sun starts cooking you or the rain
begins to fall. But you can easily double your time in the great outdoors with
this beautiful pavilion. Just think—no more rain outs during your next
barbecue! And with a roof, you can relax on dry, clean, comfortable, padded
furniture, which just can’t stand up to the elements on an open patio.
All in all, you can give your patio the feel and function of an outdoor living
room. But the best part is, this pavilion will add real beauty and value to
your home by dressing up that lonely, under used space.
OK - It's Pretty,
But Can I Build It And How Much?
While this design may look complicated to
the novice carpenter, don’t be intimidated. If you have the basic hand
power tools, can handle a circular saw and have a bit of remodeling experience,
you have the moxie to pull off this project. We’ll show you some
scribe-it, nail-it-up and cut-it-in-place techniques that greatly simplify the
tough spots and speed up the project. In fact, another carpenter and I built
the basic structure in three leisurely days and spent a fourth day finishing
the decorative column skirts. Give yourself and a helper about twice as long
and you may finish faster than you think.
Besides a carpenter’s apron
outfitted with the basic hand tools, all you need are a 4-ft. level, a circular
saw, a jigsaw and posthole digging tools. But consider renting a power nailer
for a day ($45) to save time and effort for the massive job of nailing down the
roof decking.
Comparing the before and after photos, you
can see that in addition to building the pavilion, we did some major stonework
and planting. Those improvements aside, our total materials bill came to about
$3,500.
Sandwich Framing And 2x6
Tongue-And-Groove Decking Construction
The design of this roof resembles
traditional post-and-beam construction, but without the headaches of working
with heavy, expensive timber and the tricky joinery that goes with it. The
posts, beams, rafters and ceiling ties (seeFigs. A and B) are built-in-place
sandwiches of common 2x4, 2x6, 2x8 and 2x10 smooth cedar lumber. The center
board of each sandwich is 2 in. narrower than the outer ones, which lends
attractive shadow lines and architectural “heft” to the
building.
FIG. A Roof Assembly

Click image to enlarge.

Click image to enlarge.
This triple-thick assembly method makes
the framing members very strong, which allows for longer spans and wider
spacing between members. This technique allows you to overlap and lock all the
pieces together for a very strong framework, easier nailing and tighter joints.
And, by assembling beams in layers, they’re lighter to lift. Since the
rafters are so beefy, you can space them 32 in. apart. But those wide spans
call for a roof decking that can handle those spans. Tongue-and-groove 2x6
decking (Photo 18) fills
the bill nicely because it’s very strong, reasonably priced and easy to
install. It also looks great on the inside. You can let butt ends of the roof
decking fall randomly throughout the roof; it’s not important that they
splice over framing members. But the seams will look more polished if you use a
block plane to carve a little chamfer on decking ends where two boards
meet.
This Flexible Design Is Easy
To Customize
We give the basic measurements for the
structure inFig. A, but
don’t treat them as a cutting list, because you’ll most likely have
to adjust them to fit your own home. Adjusting sizes is easy. First you get the
beams and posts laid out and in position, then you simply measure or scribe the
rest of the elements for exact lengths or angles before cutting them to length
and installing the parts. On your site, you may need to widen or deepen the
structure to miss windows or doors on the house or bridge over existing
patios.
Tip
A barbecue lid works great for drawing the
arc on the end of the beams.
You can “grow” the length or
width of the roof as much as 2 ft. without compromising structural integrity
and shrink it as much as you want. The roof lines can also be altered to miss
wall obstructions. We had to steepen the roof slope on one side to miss the bay
window you see inPhoto
2, p. 38. Under that window, the roof has a 7/12 slope (7 in. of
vertical drop for every 12 in. of horizontal distance), while the other side
has a 6/12 slope. At a minimum, you should try to have a 4/12 slope if you live
in a snowy area. Ask your building inspector for minimum slopes for your area
when you pick up the building permit. But remember that steeper pitches may
call for longer rafters and more decking. You can figure out required material
lengths when you go through the layout exercise we show in .
Selecting The Wood
We used smooth
dimensional cedar for all of the exposed framing for this pavilion. However, we
decided on stained spruce tongue-and-groove 2x6s for the roof decking because
cedar decking cost nearly twice as much. You can save about $500 by using
standard framing material for the entire structure—a smart move if you
intend to paint or stain everything to match the house.
Even though the
structural elements are exposed, you don’t need
flawless lumber for your pavilion for a clean,
handsome look. Simply select the lumber with the best faces for the edges and
sides that will show. We had all the lumber delivered (in other words, we just
got random picks from the lumberyard) and had no problem finding enough
good-looking sides and edges. If you’re dissatisfied with the look of any
of the lumber, you can always exchange it.
Lay It Out On The Ground And
House Before Digging The Footings
The easy way to determine the shape and
slope of your roof is to first lay out the “footprint” of the posts
and beams using the dimensions we give you (Photo 1). Then use a 4-ft. level
and a straight board to draw the beam locations on the walls. The height of the
bottom of the beams should be at least 6 ft. 8 in. for
“head-banging” clearance (Photo 2).
Tack 4-1/2 x 9-1/4 in. beam templates cut from plywood to the wall to simulate
beams. Then lay out the roof lines with two 2x6s tacked through the siding to
be sure:
-
The rafter tails have a minimum of 6 ft. 8
in. of head clearance.
-
The roof has at least a 4/12 slope.
-
The windows, bays or other wall
projections are spaced at least 5 in. above the rafters to leave room for
flashing.
This is the time to make final adjustments
to the roof slope and the post-and-beam locations. If everything seems OK, you
can start digging your footings.
Foundation-Grade Posts And
Floating Base Skirts
Use .60 foundation-grade treated 2x4s and
2x6s for the lower post sections and the footings (Fig. B, p. 54).
You may have to special-order them, but the added longevity is worth the money
and trouble. For the above-ground base skirt framing and sheathing, standard
.40 treated material will work just fine.
The base skirts are designed to
“float,” that is, slide up and down the fixed posts that they
encase. That’s especially important when they rest on a slab or stone
surface in cold regions where frost can lift patios when the ground freezes.
The skirts can move up and down during freeze/thaw cycles, but the posts, which
extend below frost depth, stay put—without lifting the entire structure.
So when you frame and trim the pilaster base skirts, make sure everything fits
loosely.
If the posts have to penetrate a concrete
or stone surface, cut a 20- in. square hole for digging the footings (Photo 3). Use a
circular saw with a diamond blade and don’t worry about making it pretty;
the skirt will cover the hole. To prevent settling, just be sure to pack the
soil well as you backfill around the posts.
Bracing As You Build
We show a fail-safe method of positioning
your posts so they’re square and spaced perfectly from the house and each
other. The trick is to use a jig made from the framing materials (called a
“footprint template” inPhoto 1). Initially tack the posts
to the jig (Photo 3, inset) and then later to each other
(Photo 9). Constantly check the posts throughout
the construction to keep everything square and plumb and you’ll make your
life easier as you assemble the upper parts.
The ridge assembly is especially tricky to
center and support before the rafters are in place. Use the rafter mock up
(Photo 2) to
determine the height of the bottom of the ridge and tack a temporary 2x6
support against the house to support that end of the ridge (Photo 9). The temporary brace that supports the
yard end of the ridge will most likely be taller to accommodate any drainage
slope on the patio. Cut that support a few inches longer, tack it in place and
use a long, straight board and level from the top of the house-mounted support
to mark the length. Then cut it to length and use existing and additional
supports to hold it in place before you set the ridge. A couple of 2x4s nailed
to the outside and a couple of braces will keep the ridge from slipping off the
support while you’re installing the rafters. We assembled the ridge
sandwich on the ground and lifted it into place, but it was a struggle for the
two of us! It’d be much easier to lift the boards separately and nail
them together once they’re up.
After the ridge is assembled, measure from
the ridge edges to the beams on each wall. To center the ridge perfectly,
adjust the ridge until the right and left measurements are the same. Note that
if you have to build an offset roof as we did, the ridge will no longer be
exactly centered, but you still have to make it parallel to the beams.
Materials List
|
Item
|
Qty.
|
|
LUMBER
| |
|
Premixed concrete (footings)
|
4 bags
|
|
.60 foundation-grade treated wood, 8' 2x6s (posts)
|
2 |
|
.60 foundation-grade treated wood, 6' 2x4s (posts)
|
2 |
|
.40 ground-contact treated wood, 8' 2x4s (pilaster
framing) |
3 |
|
.40 ground-contact treated wood, 4x8 sheets of 3/4" plywood
(pilaster framing) |
3 |
|
.40 ground-contact treated wood, 10' 2x2s (pilaster
framing) |
4 |
|
8' cedar 2x6s (posts)
|
2
|
|
10' cedar 2x4s (posts)
|
1
|
|
14' cedar 2x10s (beams)
|
4
|
|
14' cedar 2x8s (beams)
|
2
|
|
10' cedar 2x10s (house ledger)
|
2
|
|
16' cedar 2x10s (ridge beam)
|
2
|
|
16' cedar 2x8 (ridge beam)
|
1
|
|
12' cedar 2x6s (rafters)
|
11
|
|
12' cedar 2x4s (rafters)
|
5
|
|
14' cedar 2x6s (rafters)
|
11
|
|
14' cedar 2x4s (rafters)
|
5
|
|
16' cedar 2x6s (ceiling ties)
|
10
|
|
16' cedar 2x4s (ceiling ties)
|
5
|
|
14' cedar 1x3s (shingle molding)
|
3
|
|
12' cedar 1x3 (shingle molding)
|
1
|
|
8' cedar 2x10s (decorative braces)
|
5
|
|
12' cedar 2x6s (pilaster base trim)
|
2
|
|
12' cedar 2x4s (pilaster base trim)
|
2
|
|
8' cedar 2x10s (pilaster top cap)
|
2
|
|
8' cedar 2x2s (pilaster top collar)
|
2
|
|
8' cedar 1x3s (pilaster trim strip)
|
2
|
|
Random-length 2x6 tongue-and-groove spruce, pine or fir (roof
decking) |
750 lin. ft. |
|
HARDWARE
| |
|
10d galvanized box nails (framing)
|
3 lbs.
|
|
7d galvanized box nails (shingle molding)
|
1 lb.
|
|
10d sinkers (roof decking)
|
10 lbs.
|
|
5/16" staples (roof felt)
|
1 box
|
|
1-1/4" roofing nails (roof shingles)
|
10 lbs.
|
|
4d galvanized box nails (pilaster shingles)
|
1 lb.
|
|
10d casing nails (pilaster trim)
|
1 lb.
|
|
2,700-lb. rated USP JT (triple joist hanger)
|
2
|
|
1/2" x 2" lag screws (hanger fastenings)
|
8
|
|
1/2" x 5" lag screws (ledger to house connection)
|
12 |
|
4-1/2" USP RT 7 (hurricane tie for beam to rafter
connection) |
10 |
|
1-1/2" joist hanger nails (hurricane ties)
|
Small box
|
|
5" x 7" shingle tins (step flashing)
|
1 bundle
|
|
ROOFING
| |
|
15-lb. roofing felt (shingle underlayment)
|
1 roll
|
|
Asphalt shingles (roofing)
|
3-2/3 squares
|
|
Ridge shingles (roof ridge)
|
1 bundle
|
|
Cedar shingles (pilaster shingles)
|
3 bundles
|
FIG. B Pilaster Assembly
Finishing
Whichever wood types you decide on, think
ahead and prefinish the wood whenever possible—especially if the roof
decking sports a different finish than the framing. We put two coats of
exterior latex stain on the decking before installing it. That saved tons of
time over painstakingly cutting in cleanly around the framing. For the same
reason, it pays to apply an exterior sealer on the cedar after the structure is
up and before installing the decking. If you’re staining or painting
standard framing lumber, we suggest applying the finish before erecting the
structure and then touching up nail holes and end cuts after construction.
You’ll get a better, faster paint job and the wood surfaces that are
buried inside sandwiches will be better protected from moisture.